Februari 11. Steel girders on both sides of the drain . Part of the third lane on Jln Kamaruddin Isa removed/ collapsed? |
I KayPoh-Ed the Fair Park bridge this morning, chor2. They have now placed steel girders at the both sides of the drain.
A smoother flow of water towards the watergate.....? |
The flow towards the watergate under the bridge appears smooth flowing. That’s a good sign compared to Jan 24 when there was so much debri blocking the flow towards the watergate.
Jan 25 the day after. The blocked watergate. Only 1 side had steel girders. |
Fair Park bridge on January 24 when the Sungai Senam overflowed and flooded Fair Park |
The completion date is scheduled for 12 Mar 24. I think the contractor should be able to make the date. What do you think.
Contractor Arus Inspirasi Enterpris completion date is schedulde for 12 March 2023. |
KC